Directions: Read the following information to answer the question.
Explanation :
(A + B + C)'s 1 day's work =1/24+1/6+1/12=7/24
So, A, B and C together will complete the job in 24/7days.
Directions: Read the following information to answer the question.
Explanation :
(B + C)’s 1 day’s work = 1/9+1/12=7/36
Work done by B and C in 3 days ={7/36} x 3=7/12
Remaining work =1 -7/12=5/12
Now,1/24Work is done by A in 1 day.
So,5/12 work is done by A in 24 x{5/12}= 10 days.
Directions: Read the following information to answer the question.
Explanation :
Work done by A =1 -8/23=15/23
A: (B + C) =15/23:8/23 = 15 : 8
So, A's share = Rs.{15/23}x 529 = Rs. 345
Directions: Read the following information to answer the question.
Explanation :
Part of the work done by A ={1/10}x 5= 1/2
Part of the work done by B ={1/15}x 5=1/3
Part of the work done by C = 1 - 1/2+1/3=1/6
So, (A’s share) : (B’s share) : (C’s share) =1/2:1/3:1/6 = 3 : 2 : 1
A's share = Rs{.3/6}x 1500= Rs. 750, B's share = Rs.{2/6}x 1500 = Rs. 500.
C's share = Rs.{1/6}x 1500 = Rs. 250.
A’s daily wages = Rs.750/5
= Rs. 150, B's daily wages = Rs. 500/5 = Rs. 100.
C’s daily wages = Rs.250/2
= Rs. 125.
Daily wages of B and C = Rs. (100 + 125) = Rs. 225.
Directions: Read the following information to answer the question.
Explanation :
Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.
Suppose Tanya takes x days to do the work.
5 : 4 :: 20 : x
x ={4 x 20}/5
x = 16 days. Hence, Tanya takes 16 days to complete the work