Directions: Read the following information to answer the question.
Explanation :
Ratio of times taken by A and B = 1 : 3.
If difference of time is 2 days, B takes 3 days.
If difference of time is 60 days, B takes { 3/2} x 60 = 90 days.
So, A takes 30 days to do the work.
A's 1 day's work =1/30
; B's 1 day's work =1/90
(A + B)'s 1 day's work = 1/30+1/90
=4/90= 2/45
A and B together can do the work in
45/2= 22 1/2 days.
Directions: Read the following information to answer the question.
Explanation :
Let A's 1 day's work = x and B's 1 day's work = y.
Then, x + y = 1/30
and 16x + 44y = 1.
Solving these two equations, we get: x =1/60
and y = 1/60
B's 1 day's work 1/60
Hence, B alone shall finish the whole work in 60 days.
Directions: Read the following information to answer the question.
Explanation :
B's 1 day's work =1/12- 1/20
=2/60=1/30
Now, (A + B)'s 1 day's work =1/20+1/60
=4/60= 1/15
. [ B works for half day only ]
So, A and B together will complete the work in 15 days.
Directions: Read the following information to answer the question.
Explanation :
Suppose A, B and C take x,x/2andx/3
hours respectively to finish the work.
Then,1/x+2/x+3/x=1/2
6/x=1/2
x = 12.
So, B takes 6 hours to finish the work.
Directions: Read the following information to answer the question.
Explanation :
Whole wok is done by A in (3 x 4) = 12 days.
Whole work is done by B in (4 x 6) = 24 days.
A’s wages : B’s wages = A’s 1 day’s work : B’s 1 day’s work =1/12 :1/24 = 2 : 1 A's share = Rs.2/3 x 180 = Rs. 120.